# Dynamics 365 Testing, Part 1: Key Testing Phases During Your ERP Implementation

**Understand what each test phase is about and why it matters**

18 July 2025

## Introduction

Testing is possibly one of the most [underestimated parts](https://itfandango.com/articles/d365-fo-implementation-challenges/)
of a Microsoft Dynamics 365 ERP implementation — yet it’s a key element that marks
the difference between a solution that works and one that does not. Despite this,
too many organisations treat it as a tick-box exercise instead of a serious safeguard
to their ERP investment.

In this article, we break down the major types of testing you’ll encounter during
a Dynamics 365 F&O implementation:

 * **Main test phases:** functional testing, SIT, E2E, UAT
 * **Technical testing:** unit testing, performance testing, regression testing
 * **Other test types:** CRP, data validation, reporting, security roles, smoke 
   testing, and mock cutovers

We focus primarily on ERP implementation testing from a functional point of view(
that is, how the application impacts critical business processes), since it’s where
our expertise is. For each of those testing phases, we explain:

 * What they are
 * Why they matter
 * How things can go wrong
 * What a **worst case example** looks like

After this, we also briefly mention technical types of testing and other types of
tests and validation you should be aware of. But we will leave to future articles
any mention of specific testing tools, as well as preparation and prerequisites 
for testing.

Our goal here is to walk you through each testing stage so you can understand, prioritise,
and execute with clear ideas — before your go-live turns into go-wrong.

### Before we begin…

Testing is one challenge of ERP projects, but there are others — so in our free 
guide, we described **10 common functional issues during a D365 F&O implementation**:
what they are, why they matter, what happens if they’re neglected, and how to spot
red flags before they become critical issues. Get your free copy from the form below.

![](https://itfandango.com/wp-content/uploads/2025/05/Mockup-Functional-Health-Check-
Free-Guide-Cover-Extended-1024x635.png)

D365 F&O functional health check

10 common implementation functional issues and how to identify them

**Download your free copy!**

D365 F&O Functional Health Check

 * About you
 * About your job role
 * About your company

First Name

Last Name

Business email

Job function

Seniority level

Company type

Geographic region

_I have read and agree to the [Terms and Conditions](https://itfandango.com/terms-conditions/)
and [Privacy Policy](https://itfandango.com/privacy-policy/)_

---

## Main implementation test phases

The robustness of any Microsoft Dynamics ERP implementation is determined by its**
testing process**. And no, we’re not talking about clicking a few buttons to see
if they work and calling it a day. These testing phases are the backbone of your
assurance layer. Done right, they expose flaws before they become operational disasters.
Done wrong, they become the reason your ERP stops working on day one. Below, we 
break down the main test phases your team must treat as non-negotiable.

### Functional testing

![A technician inspecting a car engine](https://itfandango.com/wp-content/uploads/
2025/07/A-technician-inspecting-a-car-engine-1024x683.jpg)

Functional testing is a check on individual components.

Functional testing is where your system capabilities get their first serious interrogation.
The question is: can the application perform its required tasks, based on the configuration
and business logic defined? Answering it is even more important if you have designed
extensions and customisations to the standard Microsoft Dynamics 365 F&O features.

So it’s not just a matter of working without bugs, but **working as intended**. 
Consequently, functional testing should be aligned with business needs and processes
to ensure that the solution meets specific criteria. Can your users post a journal
under this and that use case? Once done, is the posting correct?

Typically, the baton here sits with your functional consultants and QA testers, 
possibly using a mix of manual and automated testing tools. Business analysts and
key users should feed into the test cases to ensure they reflect reality, helping
to create comprehensive test scenarios for thorough process validation. If your 
team is smart, they’ll also start using a **test automation platform** early for
automating and managing test cases, laying the foundation for stable tests that 
can be reused and extended later. After all, manual testers can burn out when volume
increases, and manual testing is prone to human error, compromising coverage and
quality. But automation is only possible if your processes are clearly mapped and
the design is finalised, which isn’t always true.

Functional testing is also where bugs get baked in if nobody speaks up. We’ve seen
consultants test happy paths to death, yet skip every edge case — only to realise
post-go-live that users regularly deviate from standard textbook processes. People
don’t use the ERP in a predictable, linear way. Exceptions happen, use cases and
processes have variance. The job of functional testing is to predict and anticipate
this as much as possible.

#### What can go wrong

Even seasoned teams fall into predictable traps:

 * **Test cases don’t reflect real business use.** If your testing scripts are written
   by someone who’s never processed an invoice and doesn’t understand the solution
   design, you’re setting yourself up for failure.
 * **Tests are performed on incomplete data or incorrect configurations.** While
   full data migration may not be possible when functional testing takes place, 
   testing only on a restricted set of ad-hoc records can render test outcomes meaningless
   when real-world complexity hits.
 * **Functional documentation lacks testing guidance.** Many consultants skip the
   critical step of embedding test scenarios and expected outcomes into their functional
   design documents, especially for custom features. This leaves testers guessing
   what to validate and how success is defined, which often results in inconsistent
   or incomplete testing.

![](https://itfandango.com/wp-content/uploads/2024/04/thumbs-down-solid.png)

#### Worst case example

A logistics company built a custom feature in Microsoft Dynamics 365 F&O to handle
split shipments for partial deliveries. It looked fine during design, but it was
a different story when users began using it with real scenarios after go-live. Orders
with multiple warehouses or last-minute changes triggered errors and generated duplicate
shipment records. None of these edge cases had been tested, rendering the feature
almost unusable during business operations.

Sounds familiar? We know how to help.

[TALK TO US NOW!](https://itfandango.com/contact-us/)

### Solution Integration Testing (SIT)

![A mechanic checking a car's open bonnet](https://itfandango.com/wp-content/uploads/
2025/07/A-mechanic-checking-a-cars-open-bonnet-1024x683.jpg)

SIT is verifying that all components work well together.

Once you’ve confirmed each brick works individually, it’s time to see whether the
wall holds together. Solution Integration Testing (SIT) evaluates how well your 
Dynamics 365 solution components integrate across modules and external systems. 
Testing integrations and data flows between applications is the only way to ensure
seamless operation beyond individual functionalities.

This phase is where your consultants, integration leads, and infrastructure teams
all need to talk… and they rarely do unless forced. And yet, SIT is essential. It
validates business-critical **processes that cross application boundaries**, for
example between the ERP and a third-party warehouse system. You’ll want real data,
realistic scenarios, and systems configured exactly like production. No shortcuts
here.

If you’re lucky, your project has an automation strategy in place, and integration
test runs are repeatable. Automated testing simplifies the execution of integration
tests, making it easier to manage repeated test runs. Test automation also saves
time, reduces errors, and ensures consistency across cycles. If not, you’ll rely
on fragile manual walkthroughs and hold your breath.

#### What can go wrong

SIT fails in subtle but spectacular ways:

 * **Data and data mappings are incorrect or incomplete.** Missing field, inconsistent
   formats, simplistic or made-up records can bring down the whole chain across 
   the process.
 * **Systems are tested in isolation, not together.** Even with integrations in 
   place, outputs and inputs on the two sides are simulated and never run as full
   data flows. A dangerous shortcut that increases the risk of things breaking when
   all parts are used together.
 * **No one owns the end-to-end picture.** Each consultant owns their own area, 
   so problems with interfaces are more likely to be pushed around and fall between
   the cracks.

![](https://itfandango.com/wp-content/uploads/2024/04/thumbs-down-solid.png)

#### Worst case example

A retail company implemented Microsoft Dynamics 365 F&O and integrated it with both
a new customer web portal and a third-party warehouse management system. They tested
order flows from the portal to the ERP, and separately from the ERP to the 3PL system—
but not the full journey. After go-live, orders placed by customers in the web portal
failed to reach the warehouse due to an internal interface format error. This caused
order fulfilments to stall, forcing manual workarounds for two weeks and a drop 
in customer satisfaction.

Sounds familiar? We know how to help.

[TALK TO US NOW!](https://itfandango.com/contact-us/)

### End-To-End (E2E) testing

![A mechanic doing a car inspection with checklist](https://itfandango.com/wp-content/
uploads/2025/07/A-mechanic-doing-a-car-inspection-with-checklist-1024x683.jpg)

E2E testing is your final inspection from start to finish.

Now we’re simulating real life. End-to-end testing is where you validate that** 
full business processes** flow seamlessly across multiple users, departments, and
systems. Organisations rely on E2E testing to ensure their processes meet operational
goals and function as intended across all areas. Things don’t have to just work,
but they have to work _in concert from start to finish_. This is where you run transactions
from origin to completion, verify outputs, check financial postings, and ensure 
every handoff works. It’s testing a sales order from creation, through fulfilment,
to invoicing, and finally payment collection.

Business users must be front and centre here. They’re the only ones who truly understand
how the process unfolds day to day, with all its glorious messiness. Consultants
and test managers should enable, not dominate. The focus should not just be on expected
outcomes, but on confidence: thorough **E2E testing helps build trust** among key
users by demonstrating that the system can reliably support business operations.
This confidence is key for the next phase, UAT (more on this in a second).

Done well, E2E testing is a critical stress test of your overall solution design.
It’s the first time real users from different departments work together in the new
system, using shared data and end-to-end workflows. This is where gaps in handoffs,
misaligned configurations, and shaky process assumptions come to light. It also 
shows whether teams can operate in sync or if the design falls apart under cross-
functional pressure. Better to catch that now than later.

#### What can go wrong

E2E testing is where cross-collaboration is really put to the test, and will fail
if:

 * **You test only ideal paths and simple cases.** The real world doesn’t follow
   scripts. This is where variance and exceptions must be tested too. If your process
   collapses on the first deviation, it was never fit for purpose to begin with.
 * **Cross-team coordination fails.** Logistics doesn’t know what finance is doing,
   and sales is running its own show. They don’t work on the same data, so there
   is only local testing.
 * **Data doesn’t represent real operational loads.** Made-up records won’t cut 
   it anymore. You need real or representative data from start to finish.

![](https://itfandango.com/wp-content/uploads/2024/04/thumbs-down-solid.png)

#### Worst case example

In one implementation, E2E testing was executed in silos — sales, warehousing, and
finance each tested their steps independently because some areas of the solution
were still incomplete, so users worked with placeholder configurations. When those
were later finalised, key process flows changed. As a consequence, the tests performed
during E2E were no longer valid, and people were thrown into confusion during UAT.
Test scripts had to be rewritten on the fly, eating into time meant for actual validation
and impacting the project timeline.

Sounds familiar? We know how to help.

[TALK TO US NOW!](https://itfandango.com/contact-us/)

### User Acceptance Testing (UAT)

![A man driving a car on the road](https://itfandango.com/wp-content/uploads/2025/
07/A-man-driving-a-car-on-the-road-1024x576.jpg)

UAT is your road test, done by the driver.

User Acceptance Testing is where your business decides whether to bet its operations
on the new system. This is where the **entire solution is handled to business key
users**, who has to sign it off. Can you run your company with it? UAT validates
whether the configured system supports day-to-day work in a way that makes sense
to the people doing the work. This testing round is essential for ensuring the quality
of the final system, confirming that it meets business requirements and maintains
high standards.

If business users can’t complete their core tasks without confusion, workarounds,
handholding by consultants, or Excel lifeboats — then you’re not ready. Period. 
The mistake most companies make is treating UAT as a formality, failing to cover
key cases with real data and with **key users taking ownership**. And neglecting
to rectify and retest any failed test cases. Bug fixing can’t be postponed further.

Your best UAT cycles (yes, plural, as you may need more than one round) are immersive.
You give users real data, define business-oriented test cases, and let them do their
work. By now they should be **comfortable with the new ERP** and be aware of what
they want to test and how, based on their actual day job.

Tracking UAT outcomes is how you judge your overall readiness. Now more than ever
failed test cases must be logged, analysed, and retested — not ignored. The results
reveal whether issues are isolated or systemic, and whether the risk is manageable.
This informs your go/no-go call. If users aren’t confident, they won’t be magically
ready after once the ERP is live.

#### What can go wrong

Ignore UAT at your peril. Here’s how it fails:

 * **Users are underprepared.** They’ve never seen the system, let alone tested 
   it. Insufficient human resources (not automation tools) can make this worse, 
   as there may not be enough support or training available for users.
 * **Scripts are irrelevant.** If users can’t relate to the test cases, they’ll 
   skip steps or misinterpret the intent. They should be able to understand why 
   and how they’re testing something.
 * **Push to go-live overrides concerns.** Feedback is ignored, and issues are labelled
   as “phase 2 enhancements”. Sign-off is forced, because sticking to the project
   timeline becomes more important than having a stable solution.

![](https://itfandango.com/wp-content/uploads/2024/04/thumbs-down-solid.png)

#### Worst case example

A manufacturing company pushed through UAT even though users weren’t ready. Key 
users flagged that they hadn’t completed all scenarios and weren’t confident using
the new system without support. Despite this, management forced sign-off to avoid
delaying the go-live. As a result, they got post-go-live chaos. Things failed so
spectacularly that the IT team had to work late nights processing orders manually
and firefighting issues that should have been caught weeks earlier. What should 
have been a transition became a crisis.

Sounds familiar? We know how to help.

[TALK TO US NOW!](https://itfandango.com/contact-us/)

---

## Technical testing

Functional and process testing is not all that matters. In fact, while business 
users and stakeholders obsess over workflows, data, and outcomes, technical testing
quietly ensures that your Dynamics 365 solution doesn’t collapse under its own weight.

Unlike other test phases during the ERP implementation, **technical testing** lives
mostly behind the curtain. It’s run by developers, technical architects, and infrastructure
engineers, rather than business users or functional consultants. And while it might
feel distant from day-to-day operations, ignoring this layer is like building a 
skyscraper without checking the foundations.

Technical tests validate the system’s stability, performance, and resilience. Effective
technical testing starts during software development, relies on automation, and 
uses specialised testing processes and tools to verify the robustness of your entire
Dynamics 365 ERP solution. Let’s see how.

### Unit testing

Unit testing checks the smallest building blocks: individual functions or pieces
of logic. If your developer tweaks tax calculations or writes a new method, these
tests confirm that the code is actually working without technical errors. Done right,
they catch bugs early, before they reach functional experts or end users.

### Performance testing

This is your stress test. Performance testing simulates realistic transactional 
loads and concurrent usage to verify the system won’t buckle under pressure. Slowdowns
in production after go-live are often the result of performance tests that never
happened. Performance testing also verifies the power and resilience of your overall
setup, including devices and networks.

### Regression testing

Every change, like a new feature introduced by an upgrades or developing a new customisation,
risks breaking what used to work. Regression testing ensures stability by re-running
key test cases for existing features against new builds. Automating these is non-
negotiable. Without automated testing, teams resort to selective guessing.

---

## Other types of testing

Beyond the main and technical phases, there’s a handful of specialised testing and
validation types that may not have a dedicated item in your ERP implementation GANTT
chart — but they still are important. Some of these are early-stage fit checks. 
Others are post-configuration sanity tests. Together, they round out a** complete
Dynamics 365 testing strategy**.

### Conference Room Pilot (CRP)

A pre-build simulation of core business scenarios, sometimes done even before software
selection. It’s less about bugs and more about solution fit. If your solution doesn’t
make sense at this stage, you’ve got bigger problems than testing processes.

### Data validation

More of a validation than testing it itself, it checks that migrated data is accurate,
complete, and usable. If customer records are broken or historical orders are missing
key fields, other test phases will be impacted negatively.

### Reporting testing

Ensures business reports pull correct and relevant data and deliver the expected
information — again, this is more about validation than formal testing. Naturally,
it requires that data is valid and the design is complete to generate reports correctly.

### Security roles testing

Often done in an iterative way (even after go-live), it confirms that users can 
only access parts of the system that they’re supposed to. Incomplete or incorrect
security roles can negatively impact the effectiveness of later test phases like
UAT.

### Smoke testing and mock cutover

Smoke testing confirms basic system stability after each environment deployment 
and setup. It’s your first line of defence before deeper tests begin. Mock cutover,
meanwhile, simulates the full go-live sequence (data loads, config import, batch
jobs setup) to ensure the during the actual go-live people won’t unravel under pressure.

---

## Conclusion

Not every test type applies equally to every Dynamics 365 F&O implementation. If
your organisation runs a complex third-party tech stack, SIT becomes mission-critical.
If you’re rolling out heavy customisations, functional testing will demand more 
time and rigour. The key is **not skipping or compressing the tests that matter**,
since in most cases each testing phase builds on the last and has additional requirements
to be done correctly. Shortcutting test phases is a fast track to instability, poor
adoption, and rework after go-live. Treat testing as the safety system it is — and
give it the time and focus it deserves.

**Sections:**

 * [Introduction](https://itfandango.com/articles/dynamics-365-erp-implementation-key-testing-phases/#1)
 * [Main test phases](https://itfandango.com/articles/dynamics-365-erp-implementation-key-testing-phases/#2)
 * [Technical testing](https://itfandango.com/articles/dynamics-365-erp-implementation-key-testing-phases/#3)
 * [Other test types](https://itfandango.com/articles/dynamics-365-erp-implementation-key-testing-phases/#4)
 * [Conclusion](https://itfandango.com/articles/dynamics-365-erp-implementation-key-testing-phases/#5)

![Author Profile Image](https://itfandango.com/wp-content/uploads/2024/04/Copy-of-
_DSC4810_colore_Edit-cropped.jpg)

Marco Romano

D365 F&O Independent Advisor

 * [LinkedIn](https://www.linkedin.com/in/marcoromano-itfandango/)

[Connect with me on LinkedIn](https://www.linkedin.com/in/marcoromano-itfandango/)